Make Physical % Complete editable in PWA

Please, make Physical % Complete editable in PWA schedule views.

As observed since Project Server 2010, throughout 2013 and Online as well, tasks built-in field Physical % Complete cannot be edited. It should be possible as it is editable in Project Professional and its purpose is to enter data manually.

In PWA views (access via browser) clicking on this column makes selection gray (uneditable) in contrast to for example % Complete as shown in attached screenshot.

This issue has been reported before: https://social.technet.microsoft.com/Forums/projectserver/en-US/d449410d-edec-4644-a8da-e1ccfcae0ddd

Regards, Bullvan

4 votes
Sign in
Check!
(thinking…)
Reset
or sign in with
  • facebook
  • google
    Password icon
    Signed in as (Sign out)

    We’ll send you updates on this idea

    BullvanBullvan shared this idea  ·   ·  Flag idea as inappropriate…  ·  Admin →

    0 comments

    Sign in
    Check!
    (thinking…)
    Reset
    or sign in with
    • facebook
    • google
      Password icon
      Signed in as (Sign out)
      Submitting...

      Feedback and Knowledge Base