add/update the lag through client code

please add the ability to add a lag to a tasklink. This is not available and not possible in PSI for project online. We have many times fallen short of a project online solution because this is missing.

Others have had the same issue for years as well - https://social.msdn.microsoft.com/Forums/en-US/6386b55a-4a6c-4f13-b778-beb4faf8fc20/setting-lead-lag-on-a-predecessor-using-csom?forum=project2010custprog

11 votes
Sign in
Check!
(thinking…)
Reset
or sign in with
  • facebook
  • google
    Password icon
    Signed in as (Sign out)

    We’ll send you updates on this idea

    Shannon Carey shared this idea  ·   ·  Flag idea as inappropriate…  ·  Admin →

    1 comment

    Sign in
    Check!
    (thinking…)
    Reset
    or sign in with
    • facebook
    • google
      Password icon
      Signed in as (Sign out)
      Submitting...
      • Roy Gilboa commented  ·   ·  Flag as inappropriate

        Extremely bizzare that the lag information is missing. You cannot even retrieve it (thus tyou cannot update it) from code.

      Feedback and Knowledge Base