The ability to 'Change working time'
As can be currently done in the desktop version, we need to be able to input the unavailability of resources so that the project schedule automatically takes it into account when the duration of a task is entered

12 comments
-
Anonymous commented
Would be nice if we can define weekend days as working day.
-
Anonymous commented
I don't understand why this is not even a standard option……
-
Magda commented
Has the function of "new" button been solved already?
I need to add calendar including national holidays. -
Anonymous commented
+1
Please add weekend as working days! Also when you have a task that goes through the weekend, e.g. sept 18~sept 21, the duration column is showing 2 days instead of 4 days. -
Anonymous commented
I tried to follow the procedure described in the article. But there is no "New" button on the screen.
I think Project for the Web needs to have the ability to apply multiple different work templates in a single schedule. Some tasks are weekday only, some are weekends. Some are first shift or second shift etc.
-
Anonymous commented
I can't believe this only has 6 votes so far. The lack of weekend work is the major thing keeping me from being able to try this.
-
Anonymous commented
As well as making hourly schedules for those weekend jobs!
-
Anonymous commented
This is not working for me either. I tried following the steps to create a new work hours template. When I get to step 3, there is no place to click new. Is this something being controlled by my organization?
-
Jeb Woody commented
I need to schedule crews on weekends and can't figure out how to allow that.
-
Anonymous commented
Unable to Create and apply work calendars in Project for the web.
articles on how to Create and apply work calendars in Project for the web.
Article: https://docs.microsoft.com/en-us/project-for-the-web/create-and-apply-a-work-calendarMicrosoft tech told me functionality is not working for now and support teams are aware of it and continuously working on to get this working.
-
Anonymous commented
Also need the ability to change non-working time and add multiple non-work options just like the desktop version. Some tasks can happen only during the week, and some only during the weekend.
-
Anonymous commented
Need to be able to change the number of working hours in a day (we use 7.5 not 8)